Depollution
operation in urban environment
During the construction of a building
project in the very heart of Marseilles
(13), ORTEC Generale de Depollution worked
on a site where the soils were contaminated
by heavy metals.
After marking out the area and making it
safe, our teams used a mechanical shovel
to excavate the earth, polluted mainly
by arsenic. Considering the concentrations
observed in certain points, strict
measures were taken to protect the
employees (wearing of individual protective
equipment). The earthworks had to be
carried out very progressively in order
to guarantee the stability of the land
and nearby dwellings, and to allow
construction work to continue on the
foundations of the unpolluted land.
During the soil depollution operations,
two old disused underground tanks were
discovered. To make these structures
safe, ORTEC Generale de Depollution
also carried out the pumping, cleaning
and evacuation to an approved line
of the contaminated water inside.
A total of 500 metric tons of contaminated earth was evacuated to a category 1 storage line. The final condition of the land was checked by acceptance analyses in the excavations, which enabled the building project and the construction operations to continue. |